Quantcast

Wiregrass Times

Friday, November 22, 2024

CITY OF ELBA: ATTENTION RESIDENTS - October 27

Housing10

Adobe Stock

Adobe Stock

City of Elba issued the following announcement on Oct. 27.

The City of Elba's sewer project is currently underway. The contractor's anticipated schedule for the next few weeks is below. If you see crews in these areas, please do not be alarmed.

Cleaning and Video Crew – Continue Area 1 (MLK Drive, Virgil Coleman Drive, Lee Street, Reynolds Street, Jones Street, West Street, Jackson Street, Thomas Street, Pine Dale Street, and Pine Cone Drive)

Replacement Crew – Beginning work in Area 8 starting 10/26 (Smith Street and River Drive)

If you have any questions and/or concerns, please call Pat Boothe or Sally Bane at (334) 897-2333.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS